Subcontractor Change Orders: A Notice and Log Checklist

Every subcontractor has done extra work on a verbal “go ahead.” When it goes wrong, the conversation is about what was actually asked for, when, and by whom, and the side with the better record has the easier time.

A sound subcontractor change order process is mostly habit. This post is a practical checklist for documenting change orders while the work is happening, and a simple log you can keep in a spreadsheet. The rules that apply to your job come from your contract and the law of your state, so talk to your attorney about them.

Start with your own contract

Your subcontract probably says how changes work. Before the next job, find these answers and write them on one page:

  • Who can direct a change? Many contracts require a written directive from a specific person, not a conversation with a foreman.

  • What notice is required? How many days, in what form (email, letter, a form), and to whom?

  • How is the change priced? Lump sum, time and material, unit prices, and any markup limits.

  • How is time handled? Does a change extend the schedule, and how do you ask?

  • What happens if you proceed without approval? Some contracts say you may not be paid for it.

If a clause is unclear, send it to your attorney with the question. Your attorney is the one who can tell you what it means for you. My post on using AI to review a subcontract shows how to pull these clauses out and prepare the question.

The checklist: before the extra work starts

  1. Name the trigger. Write down what changed: an RFI response, a design revision, a field condition, a request from the GC.

  2. Get the directive in writing. If the instruction came by phone or in the field, send a same-day email: “Confirming that you directed [your company] to…” Keep it short and factual.

  3. State that price and time will follow. If you cannot price it yet, say so, and give a date you will.

  4. Photograph the condition. Date-stamped photos of the existing condition are inexpensive and hard to dispute.

  5. Check the notice window. Look at the clause from your one-page summary, and send the notice inside it.

The checklist: while the work is happening

  1. Track labor and material daily. Record hours, crew, materials, and equipment on the change separately from base-contract work.

  2. Log delays and interferences that the change causes, with dates.

  3. Keep the paper trail in one place. One folder per change, with the directive, the notice, the photos, and the daily records.

  4. Report open changes weekly. A change that has been open for a month is a conversation you should start before the pay app.

The checklist: after the work

  1. Send the priced change order with the backup: quantities, rates, and the markup your contract allows.

  2. Follow up on a schedule. Put a date in your calendar to ask for the signed change order, and ask again.

  3. Carry it to the pay app. Make sure the approved amount shows up on the next application, and note any pending changes in a cover letter if your contract allows.

  4. Close it in the log only when you have been paid.

A simple change-order log

You can keep this in a spreadsheet. One row per change, with these columns:

  • CO #: your own number, used consistently

  • Job: project name and number

  • Date raised: the day the change first came up

  • Directed by: name, role, and how (email, call, field)

  • Description: one or two sentences

  • Written directive? Yes / No, with the date

  • Notice sent: date and method

  • Price submitted: amount and date

  • Time impact: days requested, if any

  • Status: open, submitted, approved, signed, paid

  • Next follow-up: a date, not “soon”

The “next follow-up” column is the one that keeps money from going stale. Sort by it every Monday.

Where AI helps

AI is good at the writing around a change, not at the judgment about it.

  • The confirmation email. Give it your notes and ask for a short, factual confirmation of what was directed, when, and by whom.

  • The write-up. Paste a week of field notes and texts and ask for a clean description of the change: what, why, when, and the cost components.

  • The weekly review. Paste your log and ask for every change that is open with no follow-up date, or open for more than 30 days.

  • The follow-up. Ask for a polite, dated reminder to the person who owes you a signature.

“Here are my notes on a change on [job]. Write a factual, polite email confirming what was directed, by whom, on what date, why the work is outside the base scope, and that price and schedule impact will follow by [date]. Keep it under 120 words and do not assign blame.”

Always check the names, dates, and amounts before you send anything. It drafts; you are responsible for what goes out.

If you want the log built for you

A spreadsheet works. If you would like a log that reminds you, ties to your pay apps, and fits how your office works, that is one of the custom tools I build to a fixed quote. For a monthly check on open changes, notices, and pay-app dates, the AI Partner Retainer includes a monthly deadline check and help when you need it.

What to do next

Book an AI Kickoff Workshop and bring your last three change orders. I will help you turn them into a log and a set of prompts your office can use on the next one. It is half a day on your own documents, on site in Oklahoma or live by video.

I am not a law firm. Talk to your attorney about your contract and your deadlines, which vary by state. You are responsible for your own notice and lien deadlines.